HI LPB SERIESLOAD POINT ASSEMBLIESOPERATION AND INSTALLATIONMANUALCorporate Headquarters 9440 Carroll Park Dr., Ste 150 San Diego,
HI LPB SERIES LOAD POINT ASSEMBLYPage 4if you are shipping the vessel fully asssem-bled on the load points. Step 4. Save the two shortest machine scre
OPERATION AND INSTALLATION MANUALPage 5Site Preparation • All mounting surfaces for the base and loading plate must be level. The distance between the
HI LPB SERIES LOAD POINT ASSEMBLYPage 6NOTE: All load point assemblies must have the same capacity when used in one scale.Principle #2 • All scales sh
OPERATION AND INSTALLATION MANUALPage 7Round Vessel with 3 Load Point Assemblies FIG. 6: THREE LOAD CELLS IN ROUND CONFIGURATIONRound Vessel with 3 L
HI LPB SERIES LOAD POINT ASSEMBLYPage 8Round Vessel with 3 Load Point Assemblies - Angle Config. #2 FIG. 8: ANGLE FOR ALL LOAD CELLS IN ROUND CONFIGUR
OPERATION AND INSTALLATION MANUALPage 9Round Vessel with 4 Load Point Assemblies FIG. 10: FOUR LOAD CELLS IN ROUND CONFIGURATION FIG. 11: FOUR LOAD
HI LPB SERIES LOAD POINT ASSEMBLYPage 10Square Hopper with 3 Load Point Assemblies - Uneven Load Distribution FIG. 12: ANGLE FOR THREE LOAD CELLS IN S
OPERATION AND INSTALLATION MANUALPage 11Typical 6 - Load Point Assembly Installation FIG. 14: SIX LOAD CELLS POSITIONED IN A RECTANGULAR CONFIGURATION
HI LPB SERIES LOAD POINT ASSEMBLYPage 12For scales that must meet NIST Class 3 (OIML Class 3) specifications:1. Maximum base plate angle variation: 0.
OPERATION AND INSTALLATION MANUALPage 13hole diameters and center distances. If you do not have Internet access, contact your local Hardy Dealer for a
1-2Local Field ServiceHardy has over 200 field technicians in the U.S., and more positioned throughout the world to assist you in your support needs.
HI LPB SERIES LOAD POINT ASSEMBLYPage 14 FIG. 17: BASE AND TOP PLATE DRAWINGSTABLE 1: BASE & TOP PLATE DIMENSIONS
OPERATION AND INSTALLATION MANUALPage 15 Step 3. Use wood or metal to create the templates. The size of the template depends on the size of the anchor
HI LPB SERIES LOAD POINT ASSEMBLYPage 16 FIG. 18: INSTALLING THE FOUR ANCHOR BOLTS FOR THE BASE PLATE Step 10. Install the correct size Jacking Nuts
OPERATION AND INSTALLATION MANUALPage 17 Step 13. Use a small spirit (bubble) level and check to see if the load point assembly is level side to side/
HI LPB SERIES LOAD POINT ASSEMBLYPage 18top plate to the support bracket. If you want to use fasteners to fasten the top plate to the support bracket,
OPERATION AND INSTALLATION MANUALPage 19 Step 5. To adjust the level of the top plate use shim stock between the top plate and the support bracket. (S
HI LPB SERIES LOAD POINT ASSEMBLYPage 20 Step 1. Use a box end wrench to loosen the adjust-ment hex nut that fastens the Anti-Lift Off Device to the t
OPERATION AND INSTALLATION MANUALPage 21 Step 6. Align the Load Cell bolt thru holes with the threaded base plate bolt holes. Step 7. Screw the two L
HI LPB SERIES LOAD POINT ASSEMBLYPage 22TroubleshootingPhysical Checks Before doing any electrical tests do the following: Step 1. Visually inspect ea
OPERATION AND INSTALLATION MANUALPage 23 Step 1. Use a millivolt meter or Integrated Techni-cian feature (See Physical Checks, Step 6) and measure the
HI LPB SERIES LOAD POINT ASSEMBLYPage 24Remedy: Step 1. Tie together the load sensor excitation (2), signal (2) and ground (1) wires.NOTE: Be careful
OPERATION AND INSTALLATION MANUALPage 25Model NumbersNOTE: The -43F/B/S indicates a stainless steel load sensor with stainless steel mounting hardware
HI LPB SERIES LOAD POINT ASSEMBLYPage 26Four Leg SystemsTABLE 6: FOUR LEG SYSTEMSSpecificationsOperating SpecificationsRated Output (F.S.) - - - - - -
OPERATION AND INSTALLATION MANUALPage 27Print the unit serial number and model number for reference when ordering parts for the HI LPB Load Point Asse
CAUTION: UNPACK WITH CAREWHEN UNPACKING, DO NOT DISCARD THE PACK-ING CASE OR ANY PACKING MATERIAL, UNTIL THE CONTENTS OF THE PACKING CASE ARE INSPECTE
Table of ContentsiTable of ContentsGeneral Information - - - - - - - - - - - - - - - - - - - - - - - - Page 1Three Load Poin
HI HLPB SERIES LOAD POINT ASSEMBLYiiElectrical Termination Cable Color Codes - - - - - - - - - - - - - - Page 26Model Numbers - - -
OPERATION AND INSTALLATION MANUALPage 1Congratulations, on your purchase of the Hardy Process Solutions Load Point Assembly. This product, is engineer
HI LPB SERIES LOAD POINT ASSEMBLYPage 2Three Load Point Types FIG. 1: FIXED PIN LOAD POINT FIG. 2: BUMPER PIN LOAD POINT FIG. 3: FREE SLIDING PIN LOAD
OPERATION AND INSTALLATION MANUALPage 3Unpacking • Do not remove the load point assembly from it’s packaging until just before installation. Although